Page 1900 - trc_centennial_deir201705
P. 1900

5.20 Dry Utilities

               from on-site renewable energy generation (PDF 21-3). The GHG emissions associated with
               energy use (electricity and natural gas) were estimated based on these assumptions. For the
               reasons discussed above, implementation of the Project would result in a less than significant
               impact to electrical services or facilities during construction or operation.

               Through coordination with SCE, two options were developed for bringing the additional
               electrical capacity: (1) upgrading the existing Bailey Substation located on an SCE-owned
               parcel within the southwestern corner of the Project site (Exhibit 5.20-2, Centennial Project
               – Dry Utility Improvements) and/or (2) upgrading the Gorman Substation and retrofitting
               the associated existing overhead transmission lines between the Gorman Substation and the
               Project site to handle the higher load. Upgrade of the Bailey Substation is considered the
               more likely solution; however, both options would continue to remain open until later stages
               of the site development process. The timing of the upgrade to the Gorman Substation and
               associated overhead lines or the Bailey Substation would be determined through ongoing
               coordination between SCE and the Project Applicant/Developer. In  either  event,  these
               improvements  would  occur  entirely  on  lands  and/or  easements  owned by  SCE, and
               therefore would not be on the Project site. The option to upgrade the Bailey Substation
               (option  1)  or  Gorman  Substation  and  overhead  lines  (option  2)  to  provide  additional
               electrical capacity to the initial development of the entire Project is described in further
               detail below.

               The Bailey Substation is a transmission relay substation, and is currently not configured for
               the distribution of voltage facilities that would be required to serve the Project. The site of
               the Bailey Substation is large enough (1.5 acres) to accommodate the required upgrade and
               it could be configured to serve the Project. The Bailey Substation upgrade would include the
               installation of a distribution transformer to carry sufficient load to the Project. Distribution
               voltage  would  then  be  extended  to  the  Project  on  the  existing  overhead  pole  line  along
               SR-138 or routed northerly overhead or underground around Quail Lake within the Project
               limits for the initial phases  of development,  then placed  underground  throughout  the
               Project. This location, if upgraded as described, would provide sufficient electrical capacity
               to serve initial Project site development. The update of the Bailey Substation would not
               require retrofitting of any overhead lines. The upgrade of the Gorman Substation would
               require retrofitting of overhead lines as described further below.


               The Gorman Substation, located approximately 3.6 miles northwest of the site, is currently
               configured for distribution voltage. However, this substation would require the addition of
               one or more additional transformers and the reconstruction of existing overhead power
               lines along Gorman Post Road from the substation to the Project. At a point just west of the
               Project boundary, the overhead facilities would take either direction along SR-138 or the
               northerly route around Quail Lake. It should be noted that, if the Bailey Substation upgrade
               were implemented, no upgrades to the Gorman Substation and its associated overhead lines
               or other off-site substation and overhead facilities would be necessary to serve any portion
               of the Project.

               Off-Site Impacts

               To provide adequate electricity for the Project, two options were developed for bringing the
               additional capacity to serve the western portion of the Project site: (1) upgrading the existing

               R:\Projects\PAS\CEN\000306\Draft EIR\5.20 Dry Utilities-051117.docx   5.20-12   Centennial Project
                                                                                                     Draft EIR
   1895   1896   1897   1898   1899   1900   1901   1902   1903   1904   1905