Page 1896 - trc_centennial_deir201705
P. 1896

5.20 Dry Utilities

               to the north of the Project site. Currently, approximately 300 dwelling units could be served
               by the existing overhead facilities associated with the Gorman Substation before a utility
               upgrade would be required (BJ Palmer 2015).

               Project Design Features


               See the Centennial Specific Plan’s Appendix 1-B, Green Development Program, and summary
               of corresponding Project Design Features in Section 5.21, Climate Change.

               Threshold Criteria

               The following criterion from the County of Los Angeles Environmental Checklist is used to
               establish  the  threshold  in  order  to  determine  the  potential  for  significance.  The  Project
               would result in a significant impact to electrical facilities and services if it would:

               Threshold 20-1        Create energy utility (electricity, natural gas, propane) system capacity
                                     problems,  or result  in the construction  of new energy  facilities  or
                                     expansion of existing facilities, the construction of which could cause
                                     significant environmental effects.


               Environmental Impacts

               Threshold 20-1        Would the project create electrical system capacity problems, or
                                     result in the construction of new energy facilities or expansion of
                                     existing facilities, the construction of which could cause
                                     significant environmental effects?

               On-Site Impacts

               The Project would place new demands on electrical service provided by SCE. Specifically, the
               Project would result in an increase in the amount of electricity consumed on the site for
               lighting and other uses, and it will create a need for new delivery infrastructure. The physical
               environmental impacts related to the implementation of necessary utility infrastructure are
               addressed as part of the Project analyzed throughout this EIR.

               Electrical Demand

               Project  construction  would  involve  limited  electricity  demands  for  equipment  such  as
               temporary lighting fixtures and tools.

               During operations, SCE estimates that buildout of all proposed land uses in the Project over
               a 20-year horizon would generate a peak increase in electricity demand of approximately
               165 MW1 at buildout (as shown in Table 5.20-1, Southern California Edison Estimate of the
               Centennial Peak Electrical Demand). The peak demand, rather than the total annual demand,
               is based on the type and quantity of land uses on the Project site which SCE determined
               would collectively generate the highest demand (i.e., peak) for electricity at one time (rather
               than the average demand of all types and quantities of the proposed land uses). The purpose

               1   A megawatt (MW) is one million watts

               R:\Projects\PAS\CEN\000306\Draft EIR\5.20 Dry Utilities-051117.docx   5.20-8   Centennial Project
                                                                                                     Draft EIR
   1891   1892   1893   1894   1895   1896   1897   1898   1899   1900   1901