Page 1899 - trc_centennial_deir201705
P. 1899

5.20 Dry Utilities

               owned parcel and reconstruction of the existing overhead power lines along Gorman Post
               Road  within  the  SCE-owned  easement  from  the  substation  to  the  Project site. Potential
               infrastructure improvements necessary to serve the western portion of the Project site are
               required by MM 20.2-2. In any event, the improvements implemented to serve the western
               portion of the Project site would occur entirely on lands owned by SCE, and therefore would
               not be on the Project site.


               In addition to the expansion or upgrade of existing facilities and construction of a future
               substation for Project buildout, an electrical distribution system would be developed on the
               Project site to supplement and, in some cases, sell power back to the regional electrical grid.
               This distribution system would be included within the main utility corridors for dry utilities
               as shown on Exhibit 5.20-2, Centennial Project – Dry Utilities Improvements. The timing for
               construction of these facilities, as well as the specific facilities’ locations and sizing, would be
               coordinated with SCE. The necessary facilities would be constructed in advance of the land
               uses that require the facilities in order to ensure that the Project’s electrical needs are met
               as the site develops. The main utility corridors for dry utilities would be located underground
               within Parkways or  Secondary  Highways,  as discussed  in the Project’s  Mobility  Plan
               (Section 3.2 of EIR Appendix 4.0-A).

               All new and upgraded on-site facilities and infrastructure would be ensured via MM 20.2-2
               and would be implemented as part of the Project within the public road system right-of-way.
               Those improvements to be constructed within the development area would not create any
               additional physical impacts beyond those addressed elsewhere in this EIR as part of the
               Project  because  implementation  of  electrical  facilities  would  be  concurrent  with  Project
               development.

               As stated above, connection to these existing facilities and development of a new on-site
               electrical distribution system will occur as part of the Project. The only other existing off-site
               facilities that would require upgrades or retrofitting to provide adequate electrical service
               to the Project would be those discussed herein (i.e., the Gorman Substation and associated
               overhead lines and/or the Bailey Substation and other off-site electrical lines).

               Continuing coordination between the Project Applicant/Developer and SCE, as required by
               MM  20.2-1, would ensure  that the new system  would  accommodate the  Project’s
               requirements,  including  construction  timing  of  these  facilities and the specific  facilities’
               locations and sizing.

               Energy Conservation in the Project

               The Project would be subject to Title 24 and CALGreen Code energy efficiency standards.
               However, as  discussed  in Section 5.21, Climate Change, the Project  has  committed  to
               compliance  with  CALGreen  voluntary  measure  A4.203.1.2.1  for  low-rise  residential
               buildings, resulting in buildings that would exceed 2013 Title 24 requirements by 15 percent
               (see  PDF  11-3  in  Section  5.11,  Air  Resources),  and  with  CALGreen  voluntary  measure
               A5.203.1.2.1 for non-residential buildings and residential buildings taller than four stories,
               resulting  in  buildings  that  would  exceed  2013  Title  24  requirements  by  10  percent
               (PDF 11-2). Renewable energy produced on the Project site will be primarily rooftop solar,
               and at minimum 50 percent of the Project’s anticipated electricity demand will be satisfied

               R:\Projects\PAS\CEN\000306\Draft EIR\5.20 Dry Utilities-051117.docx   5.20-11   Centennial Project
                                                                                                     Draft EIR
   1894   1895   1896   1897   1898   1899   1900   1901   1902   1903   1904