18           TWENTY-EIGHTH ANA'VAL REPORT


                      Distribution Construction and Operating Division
                                  THOS. BROOKS, Engineer in Charge
                        The total length of mains installed, four inches in diameter and
                    larger, was 152,944 miles, of which 128.088 miles were in the main City
                    District and 24.856 miles in the Harbor District. This is practically the
                    same as the total installed in these districts the previous year.
                        A total of 28.463 miles of mains were laid in Municipal Improvement
                    Districts, of which 14.372 miles were in the main City District and 14.091
                    miles were in the Harbor District.
                        The Department installed during the year under various Street Im-
                    provement Acts, 37.840 miles of mains in the main City District and
                    0.611 miles in the Harbor District.
                                          PIPE ACQUIRED
                    Tract No.  Owner              Length of Pipe       District
                      9300   Pacific Land Corp.     1.588 Miles      Westgate
                      7011   Vine Crest             1.010 Miles      Hollywood
                             Glendale City           .723 Miles      Eagle Rock
                       In addition, 2.725 miles of pipe were installed by private contractors
                    and turned over to the Department under Street Improvement Acts. Of
                    this amount, 2.393 miles were in the Harbor District and 0.332 miles in
                    the main City District
                                      STREET IMPROVEMENTS
                       The past year was noteworthy for the number of street improvements
                    on major traffic lanes requiring changes on important trunk lines. Among
                    them were:
                       The old 30 inch riveted steel line on the hillside above Riverside
                    Drive from the High Bridge at Fletcher Drive to the Dayton Avenue
                    Bridge was replaced by a 40 inch line in Riverside Drive. The total
                    length of this trunk line was 12,330 feet, of which 2829 feet were 14 inch
                    riveted steel pipe and 9501 feet were 5/16 inch steel bell and spigot
                   pipe with automatic electrically welded longitudinal seams.
                       A fill with a maximum depth of 18 feet was made on Vermont
                   Avenue, between Fourth and Sixth Streets, requiring the temporary
                   removal of 1250 feet 30 inch Cast Iron, for a period of over eight months.
                       The construction of the First Street viaduct over the Los Angeles
                   River, made necessary the relocation of 197 feet of the 30 inch riveted
                   steel Santa Fe trunk line around the west abutment of the viaduct.
                       Approximately 60D feet of the 24 inch Cast Iron Garvanza Trunk
                   Line were lowered, due to improvement of Fletcher Drive westerly from
                   Avenue 36.
                       Another fill on Third Street, between Berendo Street and Kenmore
  "I               Avenue, necessitated the changing of the grade of the 27 inch riveted
                   line for a distance of 598 feet, requiring the installation of 465 feet of
                   reconditioned pipe.
                       Improvement of Glendale Boulevard was the cause of lowering 54
                   feet of the 30 inch high gravity trunk line on a private right-of-way
                   south of Waverly Drive.
                       It was necessary to lower 469 feet of 24 inch Cast Iron on Angeles
                   Mesa Drive southerly from Santa Barbara Avenue, due to reestablishment
                   of street grade.
                       In connection with the effect of street improvements on the work of
                   this Division, mention is made of 118,964 feet of pipe, mostly 1 inch and
                   2 inch, used for temporary side lines during the year,
                       Three other jobs of a similar nature must be done in the near future.
                   They are: