Page 1908 - trc_centennial_deir201705
P. 1908

5.20 Dry Utilities

               SoCalGas Infrastructure
               SoCalGas anticipates that either additional feeds from the existing distribution system in the
               Project vicinity or a new system would be necessary to serve the Project’s projected demand.
               This will be determined in the future as part of the Project planning and implementation
               process. Regardless, MM 20.3-2 requires that the Project Applicant/Developer install, bond
               for, or otherwise provide on-site natural gas facilities in coordination with SoCalGas. To
               provide natural gas service to the Project, a series of transmission and distribution gas mains
               would be installed in the proposed roadways. An underground extension of gas facilities will
               need to be constructed east along Gorman Post Road from the proposed regulator station to
               the Project’s westerly entrance, where it would follow the route along with electricity and
               telephone lines through the Project site around the north side of Quail Lake. The main could
               also be extended along the SR-138 roadway, just outside the road right-of-way, easterly to
               the  initial  construction  phases  of  the  Project.  Due  to  gas  line  installation  requirements,
               transmission main extensions would be in separate trenches within proposed roadways.
               Distribution  main  extensions  would  be  installed  in  utility  corridors  (shown  on
               Exhibit 5.20-2, Centennial Project – Dry Utility Improvements). Some of these transmission
               and distribution mains may parallel each other in the same roadway. It may be necessary to
               extend a high pressure line to and within the Project site for the placement of a series of
               future  regulator  stations.  The  initial  distribution  gas  source  is  proposed  to  come  from
               connecting, or “tapping” into an existing high pressure main west of the southwest corner of
               the  site near  Gorman  Post Road, placing a regulator station (potential  easement  space
               needed of approximately 75 feet by 30 feet), and running distribution medium pressure
               and/or transmission high pressure to and through the Project site. Gas distribution efficiency
               and operating integrity require that the gas mains are looped. As the Project develops, the
               mains  may  be tied to  each other for pressure stabilization.  MM  20.3-3 requires  that an
               additional regulator station be constructed in the future to loop the distribution system for
               increased reliability.


               As discussed above, SoCalGas has stated that, with appropriate expansion of infrastructure,
               there are adequate natural gas supplies to serve the Project (SoCalGas 2006). All new and
               upgraded on-site facilities and infrastructure, including regulators and distribution facilities,
               would be implemented as part of site development and would be constructed within public
               rights-of-way. Therefore, these improvements would not create additional physical impacts
               beyond  those  addressed  elsewhere  in  this  EIR  because  natural  gas  facilities would be
               implemented within the footprint of the overall development Project.

               Energy Conservation in the Project

               The Project would be subject to Title 24 and mandatory CALGreen Code energy efficiency
               standards.  However,  as  discussed  in  the  Green  Development  Program,  the  Project  has
               committed to achieving CALGreen’s voluntary Tier 1 status, including exceeding Title 24
               requirements by 15 percent for low-rise buildings and by 10 percent for nonresidential,
               hotel,  and  high-rise  residential  buildings  (PDFs  11-5  and  11-6,  from  Section  5.11,  Air
               Resources).  Also,  a  minimum  of 50  percent  of the Project’s anticipated  electrical  energy
               demand  would  be  satisfied  from  on-site renewable energy  generation  (PDF  21-3  from
               Section 5.21, Climate Change). The GHG emissions associated with energy use (electricity
               and natural gas) were estimated based on these assumptions. A description of the ways the

               R:\Projects\PAS\CEN\000306\Draft EIR\5.20 Dry Utilities-051117.docx   5.20-20   Centennial Project
                                                                                                     Draft EIR
   1903   1904   1905   1906   1907   1908   1909   1910   1911   1912   1913